Male', Villingili, Hulhumale' & Thilafushi

Water Service Charges

Water for Domestic Consumption

No. 

Description 

Rate (Rf.) 

1

0 – 100 Liters

22.00 per cbm

2

101 – 500 Liters

70.00 per cbm

3

501 Liters and above  (>500)

95.00 per cbm

4

Fixed monthly charge

30.00


Water for Institutional Consumption

No. 

Description 

Rate (Rf.) 

1

Water consumption

75.95 per cbm

2

Fixed monthly charge

30.00


Water for Commercial Consumption

No. 

Description 

Rate (Rf.) 

1

Water consumption

101.26 per cbm

2

Fixed monthly charge

30.00


Water from Kiosk

No. 

Description 

Rate (Rf.) 

1

Water sales

100.00 per cbm


New Connection

No. 

Description 

Rate (Rf.) 

1

Domestic Water Connection &  installation of meter

1593.92

2

Institutional Water Connection &  installation of meter

3187.84

3

Commercial Water Connection & installation of meter

3187.84

4

Water connection & installation of meter (Construction sites)

1593.92

5

Construction of water meter stand

820.00



Sewerage System Service Charges

Charges for Sewer services

No. 

Description 

Rate (Rf.) 

1 

Sewerage Connection and installation of  Catch Pit 

2770.00 

2

Relocation of Sewerage Connection and Catch Pit

4410.00

3

Unblocking and cleaning of Catch Pit

295.00

4

Disconnection of  Sewerage Connection Permanently

1640.00

5

Renewal of Catch Pit

1400.00

6

Removal of Sewerage Vent Pipes (MWSC Vent Pipe only)

As per the estimate

8

Board Charge (Applicable if a road needs to be closed/ blocked)

 

 


Dewatering Services for Construction Sites

No. 

Description 

Rate (Rf.) 

1

Setup Charges

8520.00

2

Dewatering Charges

  • Package A – One Month
  • Package B – Two Weeks
  • Package C – One Week

 

25,000.00

20,000.00

15,000.00

3

Extend the period to maximum 2 day

850 / day



Charges for various other services

No. 

Description 

Rate (Rf.) 

1 

Repair to water Service Connection other than the Water Meter 

As per estimate 

2

Replacement of Water Meter due to a damage to the meter

As per estimate

3

Relocation of Water Meter (within a distance of 1m)

 

850.00

4

Relocation of Water Meter (more than a distance of 1m)

 

2600.00

5

If meter needs to be installed at a location more than 2m from the boundary

732 / m

6

Disconnection of water service on request or non-payment of bills

 

50.00

7

Reconnection of water service on request or non-payment of bills

 

50.00

8

Replacement of water tap

85.00

9

Installation of a Lockable Valve

850.00

10

Testing Water Meter

979.00

11

Testing of Water Meter (other than the one installed by MWSC)

 

300.00

12

Permanent Disconnection of Water Service

1006.08

13

Disconnection of construction meter and removal of the stand  when construction completed

 

Free

14

Board Charge (Applicable if a road needs to be closed/ blocked)